Contracts
Authorizations, change orders and payments by budget category, as of Nov 25, 2026.
Revised budget
18,450,000
Original 18,200,000
Committed
15,912,400
86% of revised budget
Uncommitted
2,537,600
14% of revised budget
Paid to date
9,284,115
58% of committed
Variance (Revised − C.W.E.)
−126,300
C.W.E. 18,576,300
| Amounts in US dollars | |||||||
|---|---|---|---|---|---|---|---|
| ID | Vendor / description | Status | Original contract | Change orders | Current contract | Paid to date | Remaining |
| 2000Design | |||||||
| *004 | Northgate Architects Architecture and interiors | Active | 1,184,000.00 | 96,400.00 | 1,280,400.00 | 1,052,318.40 | 228,081.60 |
| *005 | Hollis Engineering Structural peer review | Closed | 64,500.00 | 0.00 | 64,500.00 | 64,500.00 | 0.00 |
| *001 | Uncommitted Budget not yet under contract | Auto | 331,500.00 | −36,400.00 | 295,100.00 | 0.00 | 295,100.00 |
| Design subtotal | 1,580,000.00 | 60,000.00 | 1,640,000.00 | 1,116,818.40 | 523,181.60 | ||
| 5000Construction | |||||||
| *006 | Summit Builders, Inc. General construction, GMP | Active | 11,681,250.00 | 214,750.00 | 11,896,000.00 | 7,336,539.10 | 4,559,460.90 |
| *007 | Keystone Mechanical Imaging suite HVAC | Active | 842,300.00 | 38,900.00 | 881,200.00 | 412,880.00 | 468,320.00 |
| *008 | Granite Peak Testing Special inspections | Active | 186,400.00 | 0.00 | 186,400.00 | 121,960.00 | 64,440.00 |
| *009 | Brightline Electric Generator and switchgear | Active | 1,028,000.00 | −18,500.00 | 1,009,500.00 | 96,412.50 | 913,087.50 |
| *010 | Cedar Line Surveying Construction staking | Active | 42,800.00 | 4,650.00 | 47,450.00 | 49,115.00 | −1,665.00 |
| *011 | Vantage Low Voltage Data and security cabling | On hold | 318,600.00 | 0.00 | 318,600.00 | 0.00 | 318,600.00 |
| *012 | Hartwell Commissioning Commissioning authority | Active | 96,200.00 | 0.00 | 96,200.00 | 18,240.00 | 77,960.00 |
| *002 | Uncommitted Budget not yet under contract | Auto | 1,274,450.00 | 310,200.00 | 1,584,650.00 | 0.00 | 1,584,650.00 |
| Construction subtotal | 15,470,000.00 | 550,000.00 | 16,020,000.00 | 8,035,146.60 | 7,984,853.40 | ||
| 7000Contingency | |||||||
| *013 | Lakeshore Environmental Asbestos abatement | Closed | 124,800.00 | 7,350.00 | 132,150.00 | 132,150.00 | 0.00 |
| *003 | Uncommitted Budget not yet under contract | Auto | 1,025,200.00 | −367,350.00 | 657,850.00 | 0.00 | 657,850.00 |
| Contingency subtotal | 1,150,000.00 | −360,000.00 | 790,000.00 | 132,150.00 | 657,850.00 | ||
| Total, all categories | 18,200,000.00 | 250,000.00 | 18,450,000.00 | 9,284,115.00 | 9,165,885.00 | ||
Recent change orders
View all- Imaging suite lead shielding104,800.00CO 008*006Nov 18, 2026Pending
- Relocate rooftop unit RTU-321,500.00CO 004*007Nov 12, 2026Pending
- Curtain wall anchor revisions42,180.00CO 007*006Nov 4, 2026Approved
- Delete second transfer switch−18,500.00CO 001*009Oct 30, 2026Approved
Pending total 126,300.00, counted in C.W.E.