Metis

Contracts

Authorizations, change orders and payments by budget category.

Project
RMO-2604
Riverside Medical Office
Date
Nov 25, 2026
Revision
14

Revised budget

18,450,000

Original 18,200,000

Committed

15,912,400

86% of revised budget

Uncommitted

2,537,600

14% of revised budget

Paid to date

9,284,115

58% of committed

Variance (Revised − C.W.E.)

−126,300

C.W.E. 18,576,300

Authorizations by budget category. Amounts in US dollars.
Amounts in US dollars
IDVendor / descriptionStatusOriginal contractChange ordersCurrent contractPaid to dateRemaining
2000Design2 authorizations
*004Northgate Architects Architecture and interiorsActive1,184,000.0096,400.001,280,400.001,052,318.40228,081.60
*005Hollis Engineering Structural peer reviewClosed64,500.000.0064,500.0064,500.000.00
*001Uncommitted Budget not yet under contractAuto331,500.00−36,400.00295,100.000.00295,100.00
Design subtotal1,580,000.0060,000.001,640,000.001,116,818.40523,181.60
5000Construction7 authorizations
*006Summit Builders, Inc. General construction, GMPActive11,681,250.00214,750.0011,896,000.007,336,539.104,559,460.90
*007Keystone Mechanical Imaging suite HVACActive842,300.0038,900.00881,200.00412,880.00468,320.00
*008Granite Peak Testing Special inspectionsActive186,400.000.00186,400.00121,960.0064,440.00
*009Brightline Electric Generator and switchgearActive1,028,000.00−18,500.001,009,500.0096,412.50913,087.50
*010Cedar Line Surveying Construction stakingActive42,800.004,650.0047,450.0049,115.00−1,665.00
*011Vantage Low Voltage Data and security cablingOn hold318,600.000.00318,600.000.00318,600.00
*012Hartwell Commissioning Commissioning authorityActive96,200.000.0096,200.0018,240.0077,960.00
*002Uncommitted Budget not yet under contractAuto1,274,450.00310,200.001,584,650.000.001,584,650.00
Construction subtotal15,470,000.00550,000.0016,020,000.008,035,146.607,984,853.40
7000Contingency1 authorization
*013Lakeshore Environmental Asbestos abatementClosed124,800.007,350.00132,150.00132,150.000.00
*003Uncommitted Budget not yet under contractAuto1,025,200.00−367,350.00657,850.000.00657,850.00
Contingency subtotal1,150,000.00−360,000.00790,000.00132,150.00657,850.00
Total, all categories18,200,000.00250,000.0018,450,000.009,284,115.009,165,885.00

Recent change orders

View all
  1. Imaging suite lead shielding104,800.00CO 008*006Nov 18, 2026Pending
  2. Relocate rooftop unit RTU-321,500.00CO 004*007Nov 12, 2026Pending
  3. Curtain wall anchor revisions42,180.00CO 007*006Nov 4, 2026Approved
  4. Delete second transfer switch−18,500.00CO 001*009Oct 30, 2026Approved

Pending total 126,300.00, counted in C.W.E.